Dec 5, 2006 - Front LeftDec 5, 2006 - Front Right
December 5 - Foundation complete

Dec 5, 2006 - Foundation LeftDec 5, 2006 - Foundation Right
Garage Area                                                 Front Porch area

Dec 13,2006 - Side View


Garage FillTrees Clear

Dec 17, 2006 - Side Fill
December 16 - About 20 Dump Trucks of Fill later!

20 Dec, 2006 - Flooring DeliveredDec 20, 2006 - Flooring Ready
20 December, Flooring Materials Ready for Assembly

Dec 21, 2006 - Flooring startedDec 21, 2006 - Flooring Started

Dec 21, 2006 - Side ViewDec 21, 2006 - Garage View
December 21 - Flooring Got a Good Start in One Day

Dec 27,2006 - FrontADec 27,2006 - Front B

Dec 27,2006 - Side View
December 27, It was a beautiful day and the workers were busy all day!
Sub-Floor Finished and Walls are in Process

Dec 28, 2006 - First Wall UpDec 28,2006 - Side View
First Wall Going Up                                                                            
Dec 28, 2006 - Front LeftDec 28, 2006 - Front Right
28 December - Another busy day most of the exterior walls are up
Some interior walls up as well!

30 Dec 2006 -Front Left, No Garage Yet30 Dec 2006 - Front Right, Most Walls Up

30 Dec 2006 - Sice View
It's the End of the Year, Walls are Up Except the Garage