Dewsbury Ter.  October 06  November 06  December 06  March 07  May 07  June 07 

2 Jan 200731 Jan 2007
January 2          A Lot of Progress in just one month         January 31

2 Jan 2007 - Front Left2 Jan 2007 - Front Right
January 2 - Garage Frame Up

2 Jan 2007 - East Sidet2 Jan 2007 - West Side
         East Side of Garage             January 2              West Side Framing for Siding

6 Jan 2007 - Front Left6 Jan 2007 - Front Right
January 6 - Roof Struts Delivered


6 Jan 2007 - Front Door Looing In6 Jan 207 - Front Door Looking Out
Front Door from the Outside                                       Front Door from the Inside

6 Jan 2007 - Deck looking East6 Jan 2007 - Deck Looking West

6 Jan 2007 - Lower Deck looking East6 Jan 2007 - Lower Deck Looking West
January 6 The Deck was Completed in Two Days

78 Jan 2007 - Crane Setting Up8 Jan 2007 - Crane Ready
January 8 @ 7:30 AM - Crane Arrives to Put Up Roof Trusses

8 Jan 2007 - First Truss8 Jan 2007 - Second Truss
January 8 @ 8:35 AM - First Truss Going Up

8 Jan 2007 - Moving Along8 Jan 2007 - More Trusses
9:00 AM                                                               10:00 AM

8 Jan 2007 - Mid Day8 Jan 2007 - Mid Day 2
1:30 PM West Side of Roof Looking Good!

8 Jan 2007 - 3:00 PM A8 Jan 2007 - 3:00 PM B
3:00 PM Still Moving Along

8 Jan 2007 - 4:00 Half Done8 Jan 2007 - 4:00 Done 4 the Day
January 8 @ 4:00 PM Done for the Day, Just Over Half Done

9 Jan 2007 - Snowing9 Jan 2007 - Too Cold to Work
January 9 The Snow is Coming Down, No Work Today

10 Jan 2007 - Clear but Cold10 Jan 2007 - No Melting
January 10 The Sky is Clear, But Ice and Snow Are Not Melting!
After 3 Hours of Sun, Still too Much Ice to Work on Roof

11 Jan 2007 - Working again11 Jan 2007 - Garage Struts
January 11 @ 8:00 AM, Still Cold and Windy, But the Work Continues Today

11 Jan 2007 - Front Left11 Jan 2007 - Front Right
January 11 @ 4:00 PM, The Heavy Lifting Finished Crane Gone

13 Jan 2007 - Front Left13 Jan 2007 - Front Right
January 13 @ 4:00 PM, Cross Member Roof Supports Added

19 Jan 2007 - Front Left19 Jan 2007 - Front Right
January 19 @ 4:00 PM, Roof Peaks Added + Some Work on Eves

19 Jan 2007 - Great Room looking West19 Jan 2007 - Great Room looking East
Looking from East Side of Great Room                         Looking from West Side of Great Room

24 Jan 2007 - Front Left26 Jan 2007 - Front Right
January 24 - Sub-Roof Going up Fast

26 Jan 2007 - Great Room Looking West24 Jan 2007 - Great Room Looking East
Looking from East Side of Great Room                         Looking from West Side of Great Room

26 Jan 2007 - Front Left26 Jan 2007 - Front Right
January 26 - Black Top (Tar Paper) Almost Complete

29 Jan 2007 - Shingles Delivered29 Jan 2007 - Windows Delivered
January 29  -  Shingles and Windows/Doors Delivered
30 Jan 2007  - Windows Started30 Jan 2007  - Window Started
January 30  -  Windows are Starting to be Installed

30 Jan 2007 - Side Windows30 Jan 2007 - Side Window

30 Jan 2007 - Sun Room Afternoon31 Jan 2007  - SunRoom Morning
30 January - Afternoon in the Sun Room                 31 January  -  Morning in the Sun Room

31 Jan 2007 - Front Door installed31 Jan 2007 - Front Door
January 31  -  Front and Deck Doors Installed

31 Jan 2007 - Deck Doors installed31 Jan 2007 - Deck Doors
                                                                                     Look! Up in the Sky it's a Chimney

Whew What a Busy Month!